Questions and Answers
- Question: What is the estimated cost for this project?
Answer: The opinion of cost for each of the three alternatives for this project is $20 million.
2. Question: Due to this being a City project, will there be any cost associated with pulling a permit?
Answer: This will be a No Cost permit.
3. Question: Is Oncor furnishing the anchor bolts and templates for the street light foundations?
Answer: The street light foundations to be used on this project are Oldcastle precast, item # 1801400.